Stevens Creek Boulevard Class IV Bikeway

Transportation-Plans-Webpage.png

Project Overview

The number one priority project identified by the 2016 Bicycle Transportation Plan was a Class IV bicycle facility on Stevens Creek Boulevard along the entire length of the Stevens Creek Boulevard corridor. Phase 1, between Wolfe Road and Tantau Avenue, was completed January 2021.

Due to the length of the corridor, construction of phase 2 will be divided into 2 sub-phases:

  • Phase 2A will construct a Class IV separated bikeway along both sides of Stevens Creek Boulevard from Wolfe Road to De Anza Boulevard.

  • Phase 2B will construct a Class IV separated bikeway along both sides of Stevens Creek Boulevard from De Anza Boulevard to Mary Avenue.

Project Map

Stevens-Creek-Bikeways-Map.png

Grant Funding

The City of Cupertino was awarded $807,000 for construction of the project through the One Bay Area Cycle 2 Grant Program funded administered by the Metropolitan Transportation Commission (MTC).

Project Status

  • Design for 2A and 2B is complete.

  • Phase 2A will be advertised for bid winter 2024 and construction to anticipated to begin spring 2025.

  •  Phase 2B is pending authorization from Caltrans.