Lawrence-Mitty Park and Trial Master Plan

Lawrence-Mitty-Park.jpg

For many years the City of Cupertino has worked towards the acquisition of the 7.83-acre site located west of Lawrence Expressway and to the east of Saratoga Creek, known as Lawrence-Mitty. The property was historically used for agriculture and beginning in the 1970’s the property was used for construction stockpile storage and staging by the Santa Clara County Roads and Airports Department. The City acquired the Lawrence-Mitty site and annexed the property from San Jose into Cupertino’s jurisdiction.

The City’s plan to develop the site into a park facility includes an extension of the San Tomas Aquino/Saratoga Creek Trail, as was originally envisioned by the County of Santa Clara Parks and Recreation Department in 1999.

As a first step in the park and trail extension’s development, the City produced a conceptual plan which reflects community input and the goals laid out in the City’s 2020 Parks and Recreation System Master Plan. Throughout the development of the design, the City solicited public input via online and in-person surveys, site pop-ups, community meetings, and presented at numerous commission meetings, and to the City Council, to gather input and ideas on the park design and amenities.

The Final Conceptual Plan was approved by City Council at the July 2, 2024 meeting and is reflective of the following considerations:

  1.  Represents directives received to date from the community, commissions, and City Council;
  2.  Is consistent with the Goals, Policies, and Strategies of the General Plan and the Parks and Recreation System Master Plan;
  3.  Will not have significant negative impact on the environment; and
  4.  Provides the design intent for the future phases of design and construction of the park and trail.
  5.  The Final Conceptual Design includes an extension of the Saratoga Creek/San Tomas Aquino trail, as well as nature play areas, and picnic groves among other features.
Public Meetings and Outreach

During the early design phases of the project, many events were held. More information about those events can be found at https://engagecupertino.org/lawrencemitty

The Lawrence-Mitty Park and Trail Project was an agenda item at the following meetings. Please check the Agenda's and Minutes page to view minutes and recordings of these meetings.

  • Special joint Commission Meeting on Lawrence-Mitty Master Plan, June 13, 2022
  • Cupertino City Council Meeting, July 19, 2022
  • Bicycle Pedestrian Commission Meeting, November 16, 2022
  • Parks and Recreation Commission Meeting, November 17, 2022
  • Cupertino City Council Meeting, January 17, 2023
  • Cupertino City Council Meeting, April 16, 2024 (amend MIG contract)
  • Planning Commission Meeting, May 28, 2024 (review Conceptual Design for GP consistency and ISMND recommendations to Council)
  • Cupertino City Council Meeting, July 2, 2024 (Adopt ISMND and Conceptual Design)
  • Cupertino City Council Informational Memo published, July 24, 2025
  • Parks and Recreation Commission Meeting, May 1, 2025 (Project update)

 

Schedule
  • July 2020: Site purchase approved by council
  • December 2021: MIG contract approved
  • August 2022: Annexation completed
  • June to December 2022: Existing Site Conditions and Technical Analysis, and Community Vision explorations
  • July 2024: Conceptual Design and CEQA ISMND approved
  • November 2025: 60% construction documentation
  • April 2026: Environmental Regulatory Permitting
  • August 2026: Construction documentation and City permitting
  • November 2026: Bid and award construction contract
  • December 2026 to November 2027: Construction